4 Things Owners Should Do Before Construction Begins

Every construction project starts with an idea. Maybe your organization needs more space, your current facility no longer supports daily operations, or you’re preparing for future growth. But before construction begins, there are important decisions that can shape the project’s budget, schedule, and overall success.

From identifying priorities to understanding how construction may affect daily operations, owners play an important role in setting a project up for success.

Aaron Dugas, Preconstruction Manager at Warfel Construction, shares four ways owners can prepare before construction begins.

1. Be Clear About What Matters Most

Start with the reason for the project. What needs to work better when construction is complete?

An office renovation, for example, may begin with a list of desired improvements. Understanding the problem behind that list helps the team evaluate which changes will make the greatest difference and where there may be flexibility.

“What is the most important thing to the client and to the finished product?” is a question Aaron Dugas, Preconstruction Manager at Warfel Construction, brings to those early conversations.

The answer helps guide decisions when priorities compete. An owner may have a firm budget but flexibility in the schedule. Another may need to open by a particular date and be willing to consider different materials to make that possible.

Share those distinctions with the team, including why they matter. If a proposed alternative reduces cost but leaves the original problem unresolved, it may offer little value to the organization. A clear understanding of the project’s purpose gives everyone a better basis for weighing the options.

2. Understand Your Timeline Early

A desired opening date is a useful place to begin a scheduling conversation. Working backward from that date helps reveal the decisions and activities that need to happen first.

An owner hoping to occupy a space at the beginning of the year, for instance, may be thinking primarily about the time needed to build it. Design, permitting, and equipment availability also need to fit into that window. Bringing the design and construction teams into the conversation before construction begins helps establish whether the proposed timing is realistic.

Ask which decisions will affect the schedule and when the team needs an answer. Equipment with a long lead time may require attention well before other selections. A decision about phasing can influence how much of the building remains available during construction.

The aim is to give important choices enough time. Owners should understand the implications of a selection before committing to it, including whether it fits the budget and existing conditions. Establishing decision dates together gives the team time to explain alternatives and gives the owner room to consider them.

3. Help the Team Understand How the Space Needs to Work

A drawing can show where an entrance is located. The people using the building can explain how heavily it is used, who depends on it, and what would happen if it became unavailable.

That knowledge is particularly valuable when construction will take place around ongoing operations. Share the routines that need to continue and any limitations on access or shutdowns. Involving staff who work in the space every day can bring needs to light that might otherwise be overlooked.

An example from Dugas’s experience involved a church addition where the front entrance would close for the duration of construction. The project team had discussed the closure with church leadership, but the information had not reached the congregation. When work began, people were surprised by the change.

The lesson extends beyond choosing an alternate entrance. Before construction starts, discuss who will be affected and how information will reach them. An agreed plan is much more useful when the people arriving at the building know what to expect.

Future needs belong in these conversations as well. Sharing anticipated growth gives the team a chance to consider how decisions made today may affect the organization later.

4. Use Preconstruction to Identify Challenges Early

Bring questions into preconstruction while there is time to investigate them. A concept may look promising on paper and still need adjustments once the team considers existing conditions, cost, or the time required to obtain materials.

Owners can help by being open about assumptions. Ask what has been confirmed and what still needs to be explored. Discuss whether the proposed scope fits the available budget before becoming committed to every detail.

Sometimes the obstacle is simply that people are picturing different things. A verbal explanation may leave an owner unsure why a layout or feature will be difficult to achieve. A visual representation can make that concern easier to understand and give everyone a clearer basis for discussing alternatives.

If something is difficult to picture, ask the team to show it another way. Preconstruction is an opportunity to understand the choices ahead and work through concerns together.

Owners do not need to arrive with every answer. Knowing what matters to the organization, sharing the constraints, and being willing to ask questions gives the project team a stronger starting point.

At Warfel, those early conversations before construction begins help us understand what clients are working toward and where they need guidance. Taking the time to listen and work through decisions together helps build confidence before crews arrive on site.

Learn more about Warfel’s preconstruction approach and how early planning can help prepare your project for construction.

 

Building Quality into the Process

Building Quality into the Process: Lessons from Connections KOP

When people think about quality in construction, they often think about the final walkthrough, the punch list, or the last details completed before turnover. However,

on complex renovation projects, much of the quality work happens long before the final walkthrough begins.

At the Connections Health Solutions Montgomery County Crisis Center in King of Prussia, PA, the Warfel team used early investigation, reality capture, constructability reviews, and consistent field checks to stay ahead of potential issues. The project is a strong example of how quality is built through anticipation, planning, and communication throughout construction.

Understanding What Is Already There

Renovation work often comes with unknowns. Existing buildings do not always match available drawings, and concealed conditions can change the way a team plans, coordinates, and builds.

At Connections KOP, early demolition and field investigation helped the team better understand the actual conditions before final coordination and construction planning. This gave the project team a clearer view of what remained in place, what needed to be worked around, and where the design or budget needed to account for real conditions rather than assumptions.

Early trade partner involvement also played an important role. Trade partners were engaged before the MEP award to review incoming electrical services, evaluate existing panels, assess system capacity, and verify available ceiling space. Those findings helped the design team develop a more reliable scope and identify infrastructure risks before major commitments were made.

This early work did not eliminate every unknown. Renovations rarely work that way. But it allowed the team to enter construction with fewer untested assumptions and a clearer understanding of where attention was needed.

As Project Manager, Josh Weiner, shared, “Early investigation is always helpful to be able to identify issues that we can foresee up front.”

Building from Reality, Not Assumptions

Reality capture was another important part of the quality process at Connections KOP.

The team completed existing condition scans at multiple stages, including a post-demolition scan that became the basis for MEP coordination. This allowed new work to be modeled with precision around actual structure, utilities, and existing systems that would remain in place.

This process helped uncover important discrepancies between existing drawings and field conditions. In one instance, a rooftop unit was found to be approximately 15 feet from where it appeared in the design model. Identifying that difference during coordination helped the team address the issue before it became a more significant field challenge.

Scanning also identified existing steel columns that were not included in the as-builts or design model. With that information, wall layouts and coordinated systems could be adjusted before installation began.

“To be able to work those existing items into the model around the new allows us to actually model a building correctly and help mitigate rework or clashes in the field,” Josh W said.

Planning for the Details That Matter Most

Quality also depends heavily on knowing which details require special attention before work is put in place.

At Connections KOP, the team focused early on essential life-safety and priority wall requirements. Stantec was an excellent partner in this process, providing enlarged plans that used color to distinguish variouspriority walls and critical sequencing instructions.

The team held collaborative reviews early enough to inform bidding and ensure readiness for construction.

In the field, pre-installation meetings utilized priority-wall diagrams to clearly illustrate critical sequencing at intersections for priority assemblies and

set clear expectations before installation began. As a result of the detailed planning and communication, corrections during first-work inspections were limited and manageable.

The project also included behavioral health-specific quality requirements, including tamper-resistant devices and fasteners, pick-proof sealants, secure fixtures, recessed accessories, and special access provisions. These details matter because they support the safety, security, and long-term function of the space.

For team members and trades newer to behavioral health work, the Warfel team’s experience provided a key layer of quality oversight. Specialized requirements were discussed during regular meetings and site visits as related work approached, helping the team stay ahead of details before walls were closed or finishes were installed.

Keeping Quality Accountable in the Field

Even with strong planning, quality depends on follow-through in the field. At Connections KOP, quality work was most effective when responsibility was clear and regular attention to the work allowed issues to be reviewed in real time.

took day-to-day ownership of above-ceiling fire and acoustic reviews, using markups, observations, and follow-up tracking before ceiling closure. Because of clear communication and expectations established during pre-installation meetings, the framing contractor responded well to quality observations, allowing issues to be addressed as they were identified rather than accumulating for later correction.

That kind of accountability helped quality feel like part of the normal rhythm of the job rather than a separate process. Each step in the process was an opportunity to identify issues, communicate expectations, and address concerns before they affected the work that followed.

Learning Through the Process

A smooth project does not mean there are no lessons learned along the way.

At Connections KOP, firestopping required significant observation and follow-up with the various responsible trades. Incomplete fire caulking can become a schedule constraint when it is left until inspections or closeout, reinforcing the importance of treating firestopping as an ongoing quality responsibility throughout construction.

The team also identified an opportunity to strengthen early demolition verification. During demolition, a domestic cold-water main intended to remain was removed before the documents clearly identified it as existing-to-remain, requiring the line to be re-installed.

Both examples reinforced the value of communication, early attention to critical details, and clear assignment responsibilities before work begins. A quality mindset is not necessarily about perfection; it is about paying attention to what happens in the field, learning from it, and applying those lessons to the next project.

A Culture of Quality

Connections KOP demonstrates that quality is not a separate phase of construction, but the result of a disciplined process carried through the life of the project. Every construction project presents a unique set of conditions and execution challenges, so consistent quality cannot depend on repeating the same solutions. It depends on a culture and mindset that bring the same discipline, accountability, and care to each new challenge.