8 Steps to Pull Plan Your Project | INFOGRAPHIC

Pull Planning is an integral part of the Lean Construction process. Owners, the construction manager, and subcontractors work backwards from the agreed-upon completion date to create the most effective schedule. Follow the steps below to pull plan your project successfully.

8-Steps-To-Pull-Plan-Your-Project

1.Select Completion Date

First, identify the completion or turnover date. Write this date on a white board or sticky note and place it on the far-right side of the wall. Now, work backwards (right to left) to set the rest of your schedule.

2.Determine Milestones

What are the major milestones to completion? Write down your milestones on sticky notes, and place them on your schedule as diamonds (one point facing up). By mapping these milestones on your schedule, you’ll establish a framework with which to set the remaining activities.

3.Develop Activities List

All stakeholders should list out every activity that must take place between each milestone to make them possible. Use the question “what is the last activity that must occur before ______ can happen?” to encourage team members to think through the process. Give each team member a pad of sticky notes (don’t duplicate colors) and have them list out their activities. This allows team members to easily reorganize tasks on the schedule if necessary.

4.Develop Time Frame

How long will each step take? Apply durations to each activity without contingencies/buffer time (we’ll add these later).

5.Re-Examine Schedule

Can any activities be shortened? Did any team members include unnecessary buffers in their time frames? Can any activities be done simultaneously? Readjust these activities if necessary.

6.Determine Start Date

What is the latest possible start date based on the information on your schedule?

7.Establish Contingencies

Allocate additional time to any activities that may require buffers. Examine potential risks or uncertain timetables. Readjust start date if necessary.

8.Establish Buy-In

Assure that all team members agree to, and are advocates for, your schedule. Remember, collaboration is one of the most important principles of the Lean process.

Building Solutions: Lean Construction

When approached to run a “Lean Construction Project,” you may find yourself asking: what is Lean Construction? What will we, as a company, have to change in order to satisfy the needs of this client? How will I convince the subcontracted labor force to adopt these principles?

The definition of Lean Construction is hard to pin down. There are several sources that each have specific terminology, but it comes down to a few basic principles: elimination of waste, a culture of respect, and continuous improvement. With these ultimate goals in mind, Warfel has taken the initiative to adopt the following Lean principles in our projects:

  1. Last Planner System – Last Planner System is a collaborative method of creating and managing the project schedule. The cooperative input from the field forces performing the tasks is critical to this being successful. Monitoring of the work completed is a critical component, as “failing the schedule” suddenly becomes “failing your team.”
  2. Huddles – Small meetings where key players associated with a particular issue are gathered to collectively create a solution. This can be something as ordinary as the conflict between a light fixture and a sprinkler pipe. In this case, the electrician and plumber huddle up and find a solution to report back to the team.
  3. Big Room Meetings – these meetings are scheduled monthly, all members of the team are brought to one room to present ideas, discuss issues, and to monitor the progress of the project phase.
  4. Conditions of Satisfaction – This is one of my favorites. We all want to exceed the expectations of our clients. How can we succeed in that mission if we aren’t really sure what they want? Conditions of Satisfaction is simply a talking point that either the client, architect or builder can bring up, and document. This specifies how the success of the outcome will be gauged.
  5. GEMBA walks – “Gemba” is a Japanese term for workplace, or where the work is being performed. These are regularly scheduled walks of the construction site to harness the combined experience of the team to remove or eliminate the waste created by specific construction issues.
  6. Plus/Delta Feedback – Feedback, honestly and kindly delivered, in an effort to continuously improve. What was done well? What could be improved? Essentially, this tool is used to hold ourselves and our teammates accountable to continuous improvement.
  7. Team Building – None of the above initiatives can succeed without the implicit trust of each other, and the blunt honesty of all members of the team. All teammates must enter the Gemba Walks, Big Room, and Huddles on equal footing. Every member of the team is expected to openly share ideas, feedback, and suggestions without fear of reprisal. There is no rank. Everyone brings equal value to the project. Respect for one another is critical.

Lean Construction offers another method of planning, organizing and executing a project. While our current work is the first official Lean project for Warfel Construction, some of these principles are already familiar to our team. With the implementation of the Lean principles mentioned above, we’re confident that we will be able to meet our client’s Conditions of Satisfaction and eliminate waste, making room for a productive, more efficient job site.